Schedule
| Week | Start date | Activity | Note | In-class Quiz (During Lectures) |
|---|---|---|---|---|
| Week 1 | 10-Aug | Activity I | Monday is a Public Holiday | No (Mock quiz) |
| Week 2 | 17-Aug | Yes [#1] | ||
| Week 3 | 24-Aug | Yes [#2] | ||
| Week 4 | 31-Aug | Activity II | Yes [#3] | |
| Week 5 | 7-Sep | Yes [#4] | ||
| Week 6 | 14-Sep | Project 1 | Start Project 1 | Yes [#5] |
| Recess | 19-Sep | Rest! No activities allowed! (Dry Lab is Off Limits) | ||
| Week 7 | 28-Sep | Project 1 | End Project 1 | No |
| Week 8 | 5-Oct | Viva 1 | ||
| Week 9 | 12-Oct | Project 2 | Start Project 2 | |
| Week 10 | 19-Oct | |||
| Week 11 | 26-Oct | End Project 2 | ||
| Week 12 | 2-Nov | Viva 2 | ||
| Week 13 | 9-Nov | Nothing planned | ||